Kia Cee'd: Engine Control System / Injector Repair procedures
1. |
Turn the ignition switch OFF.
|
2. |
Disconnect the injector connector.
|
3. |
Measure resistance between the injector terminals 1 and 2.
|
4. |
Check that the resistance is within the specification.
Specification: Refer to “Specification”
|
|
In case of removing the high pressure fuel pump, high pressure fuel
pipe, delivery pipe, and injector, there may be injury caused by leakage
of the high pressure fuel. So don’t do any repair work right after engine
stops.
|
1. |
Turn the ignition switch OFF and disconnect the battery negative (-)
cable.
|
2. |
Release the residual pressure in fuel line.
(Refer to Fuel Delivery System - “Release Residual Pressure in Fuel
Line”)
When removing the fuel pump relay, a Diagnostic Trouble Code
(DTC) may occur. Delete the code with the GDS after completion
of “Release Residual Pressure in Fuel Line” work.
|
|
3. |
Remove the delivery pipe & injector assembly.
(Refer to Fuel Delivery System - "Delivery Pipe")
|
4. |
Remove the connector (A) and the fixing clip (B), and then separate
the injector from the delivery pipe.
|
• |
Do not reuse the used injector fixing clip.
|
|
• |
Install the component with the specified torques.
|
• |
Note that internal damage may occur when the component is dropped.
If the component has been dropped, inspect before installing.
|
|
• |
Apply engine oil to the injector O-ring.
|
• |
Do not reuse the used injector O-ring.
|
|
• |
Do not reuse the used bolt.
|
|
• |
When inserting the injector, be careful not to damage the injector
tip.
|
|
• |
Do not reuse the support disc.
|
• |
Do not reuse the injector rubber washer.
|
• |
When replacing the rubber washer, the steal plate (A) part should
be faced the cylinder installation part and the rubber plate
(B) part should be faced the injector body part.
|
|
• |
Do not reuse the combustion seal.
|
|
1. |
Installation is reverse of removal.
|
The injector combustion seal should be replaced new one to prevent leakage after
removing the injector.
1. |
Remove the combustion seal (A) with a wire cutter.
Grip the sealing ring carefully, pull it to form a small loop
and then cut it.
Be careful not to damage the surface of the valve sleeve with
the wire cutter.
|
|
2. |
Before the assembly of the sealing ring the groove must be cleaned using
a clean cloth.
Any coking of the injector sealing surface must be carefully removed
with a brass-wire brush.
The surfaces of the new sealing ring must be clean and free
of grease.
|
|
3. |
Place the seal installing guide (B) (SST No.: 09353-2B000) on the tip
of the injector not to damage the injector tip (A).
Push the sealing ring (C) with thumb and index finger over the conical
assembly tool until it snaps into the groove.
The complete assembly must not take longer than 2 to 3 seconds.
|
4. |
To size the sealing ring the injector is first introduced into the sizing
tool (A) (SST No.: 09353-2B000) and then pressed and at the same time
rotated 180° into the sizing tool.
|
5. |
Pull the injector out of the sizing tool by turning it in the reverse
direction to that used for the press-in process.
Check that the seal ring has not been damaged during assembly
to the injector and that no circumferential scratches are present.
Do not reuse the combustion seal.
The seal must be completely free of grease and oil.
|
|
6. |
Check the combustion seal (A) installation.
|
Description
Purge Control Solenoid Valve (PCSV) is installed on the surge tank and controls
the passage between the canister and the intake manifold. It is a solenoid valve
and i ...